Block J

Block J

Block J

Home Type
Block of flats
Size
1 and 2 bedrooms

In progress35%

Follow the progress of Block J from the first brick!

3In progressThe Brickwork
  1. Raising the scaffold and first-floor brickworkCompleted
  2. Raising the scaffold and second-floor brickworkCompleted
  • Key:
  • To start
  • In progress
  • Completed

The Brickwork

Start October 2025

Status: in progress

With a strong foundation in place, the team can now begin assembling the brickwork. This is a phase with lots of activity on the site. For the first time, the project will rise from ground level. Now that the important groundwork is complete, the team can begin to raise the scaffold, which will be used during the brickwork. The bricks will be laid to form the skeleton of the building. Before the team can begin laying the bricks and mortar, there are a few steps to take.

This milestone includes

Raising the scaffold

Start October 2025

Taking great care, the team will build a temporary framework in order to complete the brickwork from the ground to the first floor and above.

Raising the scaffold and first-floor brickwork

Start October 2025Expected to end January 2026

At this stage, the team will build from the first floor to the second, flooring and joists.

Raising the scaffold and second-floor brickwork

Start January 2026Expected to end March 2026

At this stage the team will build from the second floor to the third, flooring and joists.