Houses HT01

Houses HT01

Houses HT01

Home Type
House
Size
2 bedrooms
Delivery 1 - May 2025
8 x Houses
Delivery 2 - August 2025
8 x Houses
Delivery 3 - TBC
6 x Houses

Completed100%

Follow the progress of Houses HT01 from the first brick!

5In progressInternal Fit Out
  1. ScreedCompleted
  2. Closing up the walls and dry liningIn progress
  3. Kitchen InstallationIn progress
  4. Wall TilingIn progress
  5. Flooring coveringIn progress
  6. Powering upIn progress
  7. DecorationIn progress
  • Key:
  • To start
  • In progress
  • Completed

Internal Fit Out

Start August 2024Expected to end 8 Houses: May 2025 | 8 Houses: TBC

Status: in progress

From the outside at least, the buildings will soon begin to look like a finished article. Soon, families will start to move in, but before that, the building needs an interior. There are walls, a roof, and windows, but there is still a good deal of work to be done before residents move in.

This milestone includes

Screed

Start August 2024Expected to end August 2024

During this step, a concrete finisher performs a process called screeding. This is cutting off excess wet concrete to bring the top surface of a slab to the proper grade and smoothness.

The first fix: plumbing and electrics

Start October 2024Expected to end October 2024

Now that the houses have a structure, workers will install the essential components to make them into homes. This includes the electrics, plumbing and ventilation. Part of the first fix is the installation of cables, wires, pipes and other hidden fixtures.

Closing up the walls and dry lining

Start October 2024Expected to end April 2025

Before the second fix, plasterers will carefully close up and finish the interior walls.

Kitchen Installation

Start January 2025Expected to end May 2025

During this process, the team will install the kitchens and internal doors, skirtings and architraves.

The second fix

Start January 2025Expected to end 8 Houses: May 2025 | 8 Houses: TBC

As soon as the plasterers and carpenters have completed the dry lining, the skilled workers will return to convert wires into sockets, and pipes into taps.

Wall Tiling

Start January 2025Expected to end 8 Houses: May 2025 | 8 Houses: TBC

Tiles will be added to the kitchen and bathroom walls.

Flooring covering

Start February 2025Expected to end 8 Houses: May 2025 | 8 Houses: TBC

Powering up

Start January 2025Expected to end 8 Houses: April 2025 | 8 Houses: TBC

For the first time the building will be connected to the Grid. Water, gas and electricity will flow through its pipes, and there will be light, heat, hot and cold water.

Decoration

Start February 2025Expected to end 8 Houses: May 2025 | 8 Houses: TBC

At this point the painters and decorators will return to add the final touches to the interiors. At this stage, the project is in the final phase of preparation for the first householders. Before we can allow anyone to cross the threshold however, we have our own housekeeping to complete. Stage Six: The completed build.