Houses SL03

Houses SL03

Houses SL03

Home Type
House
Size
3 bedrooms

In progress95%

Follow the progress of Houses SL03 from the first brick!

1Completed in January 2025Foundations
  1. Site LevellingCompleted
  • Key:
  • To start
  • In progress
  • Completed

Foundations

Start April 2024Expected to end January 2025

Status: completed

After months of careful planning, the site is primed and ready for the first pour. Standing on the edge of the site it's easy to look at the footprint and imagine the shape of the building to come. Engineers and builders are waiting for the arrival of the steel and concrete. This is an exciting time and a few months from now this area will transform as the first new homes are built. Before the big pour, however, there are a few task to complete.

This milestone includes

Soil Testing

Start July 2022Expected to end July 2022

In accordance with UK Law, the team will make sure the soil meets UK standards and is free from toxins.

Site Levelling

Start July 2022Expected to end July 2022

Using sophisticated equipment, the engineers will ensure all measurements are accurate. In particular, the heights must be correct in relation to each other.

Site Clearing

Start July 2022Expected to end July 2022

Removing any unwanted debris.

Concrete Groundfloor Slabs

Start November 2024Expected to end January 2025

Reinforced by steel, this poured concrete layer will be between 100 and 500mm thick.